Hyperscale Data warns it may run short of cash after selling its last bitcoin

The bitcoin miner needs about $74.8 million more to finish an AI data center in Michigan by March.

· Orange Wire desk

Hyperscale Data, a company that mined bitcoin in Michigan, says there is substantial doubt it can keep operating over the next year. The warning is in its quarterly report, filed with the SEC on November 18, CoinDesk reported.

The company, listed on NYSE American as GPUS, has already sold all of its bitcoin. Its last sale, about 211.6 BTC, raised about $16.0 million in early November, according to the filing and a company press release.

From bitcoin to AI

In total it sold about 1,113 BTC from late July for about $74.4 million, the press release says. The money went to paying down debt and building an AI data center at its old mining site in Michigan.

  • The project will supply about 20 megawatts of data center capacity to an AI customer, the filing says.
  • It is expected to cost about $122.1 million. The company had paid about $47.3 million by the end of October.
  • It needs about $74.8 million more between November and March, CoinDesk reported from the filing.
  • The first 10 megawatts are due to switch on in December, the company said.

The company has described the contract as worth up to $1.2 billion. That figure assumes the customer uses two five-year extensions after the first 10 years, CoinDesk reported.

The cash gap

Hyperscale had about $17.3 million of unrestricted cash on September 30, the balance sheet in its filing shows. Its liabilities due within a year came to $231.2 million. It lost about $62.1 million in the first nine months of 2026.

Management is looking at selling shares, borrowing or selling assets to fill the gap, CoinDesk reported. The company stopped mining in Michigan on September 1, the filing says. It still mines bitcoin at a site in Montana, and expects any bitcoin it holds to come mainly from there, the press release says.

Why it matters

Many public miners are turning old mining sites into data centers for AI companies, whose contracts pay steadier income than mining. Some sell their bitcoin to pay for the switch. Hyperscale sold its whole bitcoin reserve and still says it may not have enough cash to finish the job.

Sources (4)

Not financial advice. How we report and check stories.

Found this useful? Tip the desk in sats at our Lightning address, tips@orangewirebtc.com. Tips are voluntary. They buy no extra content and no influence over coverage.

Liked this? Get five stories like it every week, plus one chart and one explainer.

Your email addressSubscribe

Free. Unsubscribe anytime.